Wirtgen Slipform Paver SP 64i in the USA

A perfectly even runway

Inset pavers such as the SP 94i are ideal for the cost-efficient building of large concrete pavements, for instance on highly resilient motorways and runways.

Missouri, USA // Jefferson City

With more than 30,000 take-offs and landings a year, Jefferson City Memorial Airport (JEF) is one of the most heavily frequented airports in the US state of Missouri. Thousands of visitors travel through it every day on their way to the government and congress offices in the state capital on the Missouri River. At the end of April 2015, work commenced on the reconstruction of a runway approximately 1800m in length. It marked the premiere of one of the first type SP 94i slipform pavers to be delivered.

The new WIRTGEN SP 94i slipform paver excels in the reconstruction of a runway in Missouri, USA.

Precision work after just two days of set-up

The owner of the slipform paver, the Lehman Construction Company, got to work on the site as soon as the two days required for set-up of the machine were over. The 25cm-thick concrete layer was paved on a prepared base course which was also 25cm thick. Apart from dowel bars spaced at transverse intervals of 45cm and longitudinal intervals of 3.8m, the runway does not have any continuous reinforcement. Some 20,000m³ of concrete in total was laid on the runway, which is 1.8km long and 30m wide. “The specification for surface evenness allowed for a maximum permitted deviation of 7.0in per mile (18cm per 1.61km),” explains Tim Nash, Director Concrete Products WIRTGEN, WIRTGEN AMERICA. “Since the machine first went into operation, we have not had a deviation of more than 1.0in/mile (2.54cm per 1.61km) on any paving job. Usually, in fact, it was 0.0in.” Lehman achieved this high standard of evenness with practically unchanged factory settings, i.e. with no major modifications on the job site. The productivity was also impressive: each day the SP 94i paved concrete over an area up to 750m long and 7.50m wide. Due to high daytime temperatures of over 30°C, paving largely took place during the night hours.

Edges at 90° angle

The authorities also had stringent requirements on how the edges of the runway were shaped — the angle was to be exactly 90°. “The representatives of the construction inspection authority confirmed to us that they had never yet seen such precise edges,” Tim Nash recalls. “A vertical concrete edge is crucial for laying the next slab,” confirms John Gibson, Test Engineer at Burns & McDonnell, the company responsible for inspecting the construction work. “And this machine delivered a very good edge.” The SP 94i performed impressively in every respect: “The weight of the machine and the well-thought-out design ensure an outstanding surface. The quality is more or less built in, you can see that even in the tiniest details. It’s very impressive."

Dowel bar inserter (DBI): Inserting dowel bars and longitudinal joint bars automatically

While in Jefferson City, the dowel bars had been placed in a reinforcement cage beforehand, with the slipform paver subsequently laying the spread concrete on top, the SP 94i also offers the option of inserting dowel bars and longitudinal joint bars in one operation during the concrete paving process.
The dowel bar inserter (DBI) integratedin the frame of the machine inserts the dowel bars in the correct position in order to secure the height of adjacent slabs. Longitudinal joint bar inserters: inserted automatically, the longitudinal joint bars prevent pavement slabs from moving apart.

Investment in leading technology pays off

Lehman’s decision to buy the new WIRTGEN SP 94i slipform paver has been thoroughly vindicated. Kenny Lehman, Owner and Director of the Lehman Construction Company, put it this way: “We wanted to try out something new, because I’d heard that this machine could achieve a smoother surface than machines of competitors. With the SP 94i, we’re actually achieving even better surface accuracy than we had expected.” The process of setting the concrete paver up at the job site — which includes positioning and zeroing the crawler tracks and the swivel arms — is quick and easy with the SP 94i. “The crawler units work very well and the set-up time for the sensor system is short. All the settings can be done very quickly,” says Lehman.

The evenness that the SP 94i achieves is outstanding. That comes down to the innovative technological features of the new slipform paver. The uniform spreading of the concrete by the spreader plough and the slab paving kit with wear-resistant pad also play an important role.

Adam Carroll, Head of Department Lehman Construction Company

Boosting competitiveness with the SP 94i

“The specifications in our contracts are frequently very strict, so everything has to be just so,” the owner added. “This machine will boost our competitiveness. The requirements on motorways can be met much more easily with the SP 94i. We’re really happy with this slipform paver.” The first project was already a complete success — we’ve delivered a first-class runway. Now the pilots taking off and landing at Jefferson City Memorial Airport can put this to the test.

Highlights of the SP 90 series: The mid-range WIRTGEN inset pavers

  • Pave width: 3,500 — 9,500mm standard
  • Layer thickness: up to 450mm standard
  • Operating concept: selfexplanatory with clear, language-neutral symbols
  • Eco mode: load-dependent engine management reduces fuel consumption and noise emissions
  • Machine control system: latest generation, automatically recognizes the machine configuration, sets the optimum machine parameters
Show more
Job site details
The job site:
Project dimensions
Length of section:
Width of section:
Working parameters
Thickness of concrete layer:
Reinforcement:
Pave width:
Paved material quantity:
Area paved:
Equipment
WIRTGEN
Project dimensions
Length of section:
1.8 km
Width of section:
30 m
Working parameters
Thickness of concrete layer:
25 cm
Reinforcement:
Dowel bars at transverse intervals of 0.45 m and longitudinal intervals of 3.8 m
Pave width:
7.5 m
Paved material quantity:
20,000 m³ of concrete (approx.)
Area paved:
5,600 m² per work shift (approx.)
Equipment
WIRTGEN
SP 94i slipform paver
SP 94

Inset Slipform pavers

Exhaust emissions category
EU Stage 3a/US EPA Tier 3
Paving width
3,500 - 9,500 mm
Layer thickness
0 - 450 mm