WIRTGEN GROUP Cold In-Place Recycling

Eco-Friendly Road Rehabilitation with Cold Recycling Train in Portugal

Rural road ER 361, which passes through the town of Monsanto, about 100 km north of Lisbon, Portugal, was in need of structural rehabilitation along 2.7 km in both directions. The contracting public authority, Infrastructuras de Portugal, had planned around 12 weeks for the repair work. The road construction experts from the contracting company Pragosa completed the job in just four days using the cold recycling method, however.

Wirtgen W 380 CR Cold Recycler Rehabilitates the Road Surface in Record Time

The heart of the cold recycling train is the new Wirtgen W 380 CR, which made its debut for Pragosa on this job site. It is capable of recycling the old layers of the road in just one pass. A Vögele paver was responsible for paving true to line and level, and several Hamm rollers carried out the final compaction.

Milling, processing, paving, and compacting – eco-friendly road rehabilitation with technology from the WIRTGEN GROUP

Before construction work began, we lined up all the machines in the construction company’s yard and briefed the entire job site crew on the machine technology and techniques. Professionally prepared for the project requirements, the crew and WIRTGEN GROUP machines worked together perfectly and the project was thus completed efficiently and with excellent results. I have been all over the world and seldom worked with such a skilled and well-rehearsed team.

Mike Marshall, Recycling expert at WIRTGEN GmbH

Time Savings Key to the Success of Cold in-Place Recycling Process

Time is another factor in the success of cold in-place recycling, as this application is called. Shortening the duration of the project from 12 weeks to 4 days was only possible because almost no material had to be transported. The actual job site planning had envisaged that both lanes would be excavated to a depth of 54 centimeters and rehabilitated from scratch. This would have resulted in 7,500 m³ of material that would have needed to be transported away from the job site and replaced with new material. Replacing the material, including all the associated work, resulted in the planned construction duration of 12 weeks. Cold in-place recycling eliminates the need to replace existing material, as it can be reused right on the job site. By adding lime and foamed bitumen as binding agents and using all the existing materials, a new, high-quality construction material is produced on the spot. The new bitumen-stabilized material (BSM) serves as the new “backbone” of the busy road, and is immediately fit for traffic again after completion of a construction section.

Flexibility Thanks to Adjustable Working Widths

The width of the lane varied between 2.75 meters and 3.25 meters on the job site. As a result, the W 380 CR cold recycler was equipped with a milling drum unit with a working width of 3.2 meters instead of its standard unit with a working width of 3.8 meters. The innovative MCS system even made it possible to switch the units right on the job site.

The University of Minho was responsible for designing the mix for the new BSM layer and collecting samples of the existing road structure. In the process, they determined that the road bed still had enough bearing capacity that a BSM layer plus a new asphalt surface layer represented a long-lasting alternative to the conventional, cost-intensive process of constructing a new road. To produce the new BSM layer, 7 kg of lime per square meter needed to be added to the mix. The lime was applied directly to the old road surface prior to the mixing process. With its extremely precise spreading unit, a Streumaster SW 5 RC mounted to a John Deere tractor ensured that the lime was evenly distributed. The maximum spreading width of 2.5 meters required the spreader to make two passes to cover the CR’s working width of 3.2 meters. By carefully discharging the material at the right spreading width, the crew achieved a high degree of spreading accuracy, which kept costs as low as possible.

The rear-mounted SW 5 RC binding agent spreader precisely distributes the required amount of lime in front of the cold recycling train.

Cold Recycling Train with Wirtgen W 380 CR Cold Recycler

The W 380 CR then milled 16 centimeters deep through the damaged asphalt surface layer into the binder course. “The working depth of the cold recycler was set to 16 centimeters in order to produce a BSM layer with sufficient bearing capacity,” says Mike Marshall. After adding only 2.6% foamed bitumen and water, the lime was mixed in directly. Using the down-cut method, the new homogeneous road bed was mixed from the existing material consisting of the surface course and parts of the binding agent with the aggregates. The tremendous engine power of the CR paired with the highly efficient and powerful foamed bitumen spray bar allowed the machine to advance at a rate of 5 meters per minute. In the process, the CR produced around 320 tons of high-quality BSM mix per hour. “Foamed bitumen was selected as the binding agent. This offers numerous benefits in terms of processing capabilities and cost-effectiveness. In addition, cold processing significantly reduces carbon emissions,” explains Mike Marshall.

Paving with the VÖGELE Paver

The flexibly adjustable conveyor of the W 380 CR transported the 320 tons of BSM into the hopper of the Vögele SUPER 1900-3i following behind it. At its maximum capacity of up to 900 tons per hour, the paver was able to work in a particularly fuel-efficient manner in ECO mode here. The TP2 extending screed with Vögele high-compaction technology that was used features a tamper and two pressure bars. It was responsible for thoroughly precompacting the surface and could be perfectly tailored to the properties of the recycled material thanks to the ability to adjust the speed and stroke. Ideal leveling systems paired with the compact design of the SUPER 1900-3i made it possible to follow the CR in the lane and pave the new lane true to line and level.

Compaction and Sealing with Hamm Tandem and Pneumatic Tire Rollers

The paver was followed by three Hamm road rollers to complete the construction project. An HD+ 110i tandem roller with a smooth drum was used to first seal and stabilize the perfectly paved layer. Two GRW 18 pneumatic tire rollers were then used for final compaction. The impressive compaction performance of the Hamm rollers produced a seamless transition to the unmilled lane. The surface quality of the BSM layer was so good after only a few passes of the pneumatic tire rollers that it was possible to open the lane to traffic. Even a fully loaded forklift truck operated by a local company was able to drive on the recycled roadway without damaging the surface.

After the cold recycling train, the final step was to apply the fog seal – a diluted bitumen emulsion used to protect the BSM layer from oxidation and weathering. The fog seal did not need to be removed before paving over with the new 5-centimeter-thick surface layer. It also serves as a binding agent and can withstand heavy traffic for a long time. In this case, over five months – until the surface layer was finally paved.

The small town of Monsanto significantly benefits from the construction project. The construction work was completed in just four days, despite the road – with its tight curves and cobblestone driveways – posing a significant challenge.

Using conventional methods, rural road ER 361 would have been impassable at this point for 12 weeks, meaning that residents and businesses would have had to deal with major problems and delays. Thanks to cold in-place recycling, the houses were only separated from the road for half an hour before everything went back to normal. No holes from excavators, no barriers – it was even sufficient to only close the lane that was being worked on.

Foreman Pedro Silva from construction company Pragosa and WIRTGEN recycling expert Mike Marshall (left) agreed that cold in-place recycling with the W 380 CR is extremely fast and cost-effective.

Cold in-Place Recycling – the State-of-the-Art Road Construction Method

The environmental benefits of cold recycling are abundantly clear. According to Pragosa, it saved around 98% of the carbon emissions compared to the conventional construction method. This was primarily due to the fact that the construction material was reused on site, which otherwise would have had to be transported to and from this job site by truck – in around 1,500 separate trips. In addition, there were no landfill costs for disposal and mining costs for the new material. In other words, using this method also conserved natural resources and significantly cut costs.

Job Site Details
The job site:
The job site:
The town of Monsanto, about 100 km north of Lisbon, Portugal
Surface area rehabilitated:
Surface area rehabilitated:
Approx. 13,000 m²
Recycling depth:
Recycling depth:
15 – 17 cm
CR 380 working width:
CR 380 working width:
3.2 m
Quantity of lime prespread:
Quantity of lime prespread:
7 kg/m²
Foamed bitumen added:
Foamed bitumen added:
2.6% = approx. 140 kg/min
Working speed:
Working speed:
5 m/min
BSM production:
BSM production:
320 t/h
Daily output:
Daily output:
4,000 m²
Machines Used:
Machines Used:
1x WIRTGEN W 380 CR
1x STREUMASTER SW 5 RC
1x JOHN DEERE 8270 R tractor
1x VÖGELE SUPER 1900-3i
1x HAMM HD+ 110i tandem roller
2x HAMM GRW 18
W380CRi 00001
W 380 CRi

Cold recycler

Exhaust emissions category
EU Stage 5/US EPA Tier 4f
Working width max. 12 ft 6 in
Working depth
13.8 in